Osisko Gold Group board approves construction of the Cariboo gold project in British Columbia

Osisko's board approved building Cariboo in B.C.; it estimates C$990 million of capital remaining and a C$201 million surplus if financing closes.

The Mining Dispatch desk · · 1 min read

Regions: Canada

Small drilling rig with a slim mast on a distant rocky forested ridgeAI illustration
Illustrative image generated with AI. It does not show the event described. AI-generated illustration.

Why this matters: our read

The construction decision comes before two parts of its financing are final: the share sale awaits exchange acceptance and the prepayment terms are non-binding. Osisko's own plan shows a surplus only if those close, so watch the closing, a definitive prepayment agreement and whether the longer schedule holds.

Osisko Gold Group Inc. said on September 14 that its board approved construction of its Cariboo Gold Project in British Columbia. It expects a first gold pour in the first quarter of 2029, after 30 months of construction against 24 in the April 2025 feasibility study.

Osisko estimates the remaining capital obligation at C$990 million from August 1, 2026, net of about C$272 million incurred to July 31. The study put initial capital at C$881 million; Osisko says the two figures are on different bases, and that its update reflects costs incurred, engineering and procurement progress, inflation and reclassified operating costs. The estimate includes 16.5 per cent contingency and assumes about C$117 million of mining equipment is leased, under non-binding term sheets.

Osisko lists sources of up to C$1,637 million, including about C$837 million of cash at June 30, against uses of C$1,435 million, a projected surplus of about C$201 million. Osisko says that depends on the share sale closing, a definitive gold prepayment agreement and equipment financing assumptions.

Trafigura affiliate Urion Investments Holdings agreed to buy shares for about US$30 million (9,554,141 at US$3.14), subject to TSX Venture and New York Stock Exchange acceptance. Barkerville Gold Mines agreed non-binding terms with Trafigura for a gold prepayment of up to US$120 million at SOFR plus 6.00 per cent.

Sources

We link to and summarize; the publishers own the original reports.