Daily edition Subscribe to the weekly digest
Mining Dispatch

Mining news, read in full and curated daily.

Commodities

Ivanhoe cuts 2027 Kamoa-Kakula copper guidance to 300,000-350,000 tonnes

Ivanhoe Mines lowered 2027 Kamoa-Kakula copper guidance to 300,000 to 350,000 tonnes and cut capacity at the three existing concentrators.

The Mining Dispatch desk · · 1 min read

Regions: Africa, Canada

Conical stockpile of copper-green ore in a gravel yard under a grey skyAI illustration
Illustrative image generated with AI. It does not show the event described. AI-generated illustration.

Why this matters: our read

Ivanhoe now needs the Phase 4 expansion to get back to about 500,000 tonnes a year. Watch whether the eastern-side mining start holds at the first quarter of 2028 and whether the open pit delivers first ore in the third quarter of 2027.

Ivanhoe Mines said in a news release dated November 3, 2026 that Kamoa-Kakula should produce 300,000 to 350,000 tonnes of copper in 2027. It put the C1 cash cost at $2.50 to $3.00 per pound of payable copper, up from $2.10 to $2.50, citing diesel prices, lower grades and lower output. The third quarter of 2026 averaged $3.00.

The three existing concentrators are now rated at 400,000 to 450,000 tonnes a year. Ivanhoe said Phase 4 engineering starts in the first quarter of 2027 and construction takes 18 to 24 months from project approval, to reach about 500,000 tonnes. Open-pit first ore is expected in the third quarter of 2027, and an updated life-of-mine plan is due in March 2027.

Canadian Mining Journal reported the range is 19% below the earlier 380,000 to 420,000 tonnes, and that 2026 output is about 290,000 tonnes, the bottom of the prior 290,000 to 310,000 range. It also reported production mining on Kakula’s eastern side slipping to the first quarter of 2028 from the fourth quarter of 2027. Details come from Ivanhoe’s own news release and have not been independently verified.

Sources

We link to and summarize; the publishers own the original reports.